CONTENTS
6. SUMMARY OF MONITORING EXCEEDANCE, COMPLAINTS, NOTIFICATION OF SUMMONS AND PROSECUTIONS.............................................................................................................................................................. 20
Appendix A Master Programme
Appendix B Overview of Desalination Plant in Tseung Kwan O
Appendix C Summary of Implementation Status of Environmental Mitigation
Appendix D Water Quality Graphical Presentation
Appendix E Site Inspection Proforma
Appendix F Waste Flow Table
Appendix G Summary of Exceedances
Appendix H Complaint Log
Appendix I Event/Action Plan for Noise and Water Quality Monitoring Exceedance
A1. The Project, Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (TKODP), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (EP No. FEP - 01/503/2015/A) for the construction and operation of the Contract.
A2. In accordance with the Environmental Monitoring and Audit (EM&A) Manual for the Contract, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Contract.
A3. This is the 1st Annual EM&A Review Report, prepared by ASCL, for the Contract summarizing the monitoring results and audit findings of the EM&A programme at and around Tseung Kwan O Area 137 (TKO 137) during the reporting period from 16 March 2020 to 31 March 2021.
A4. The EM&A programme for this contract has covered environmental monitoring on water quality, construction noise level at selected NSRs, and Contractor¡¦s environmental performance auditing in the aspects of construction dust, construction noise, water quality, waste management, landscape and visual and ecology.
A5. A summary of the environmental monitoring and audit works undertaken in the reporting period are summarized in Table I.
A6. No construction noise monitoring was conducted during the reporting period since there are no Contract -related construction activities undertaken within a radius of 300m from the monitoring locations.
A7. No water quality monitoring was conducted between March 2020 to February 2021, since the commencement of marine construction and dredging activities for the Project was scheduled in March 2021. All water quality monitoring was conducted as schedule during the reporting period.
A8. No landfill gas monitoring was conducted during the reporting period since SENT landfill Extension is still under construction, the landfill gas monitoring will be conducted after the commencement of operation of the SENT Landfill Extension.
Environmental Monitoring works |
Frequency |
Noise Monitoring |
N/A |
Water Quality Monitoring |
13 |
Landfill Gas Monitoring |
N/A |
Environmental Site Inspection |
55 |
A9. No construction noise monitoring was conducted during the reporting period. No Action Level exceedance was recorded during the reporting period.
A10. The EM&A works for water quality were conducted during the reporting period in accordance with the EM&A Manual.
A11. All water quality monitoring was conducted as schedule in the reporting period. Six (6) of the general water quality monitoring results of suspended solids (SS) obtained had exceeded the Action level. One (1) of the general water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.
A12. All Action and Limit Level exceedance was concluded to be unrelated to the Project. Details of the exceedance could be referring to Appendix O of the represent Monthly EM&A Report.
A13. No landfill gas monitoring was conducted during the reporting period.
A14. No environmental complaint was received during the reporting period.
A15. Neither notifications of summons nor prosecution was received for the Contract.
A16. There was no change to be reported that may affect the on-going EM&A programme.
1.1. Background
The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading as AJC Joint Venture (AJCJV) is contracted to carry out the Design, Build and Operate First Stage of Tseung Kwan O Desalination Plant (DPTKO) under Contract No. 13/WSD/17 (the Contract).
Acuity Sustainability Consulting Limited (ASCL) is commissioned by AJCJV to undertake the Environmental Team (ET) services as required and/or implied, both explicitly and implicitly, in the Environmental Permit (EP), Environmental Impact Assessment Report (EIA Report) (Register No. AEIAR-192/2015) and Environmental Monitoring and Audit Manual (EM&A Manual) for the Contract; and to carry out the Environmental Monitoring and Audit (EM&A) programme in fulfillment of the EIA Report¡¦s EM&A requirements and Contract No. 13/WSD/17 Specification requirements.
Pursuant to the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection granted the Environmental Permit (No. EP-01/503/2015) and Variation of Environmental Permit (No. EP-01/503/2015/A) to Water Supplies Department (WSD); and granted the Further Environmental Permit (No. FEP-01/503/2015/A) to AJCJV for the Contract.
1.2. The Reporting
Scope
This is the 1st Annual EM&A Review Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 16 March 2020 to 31 March 2021.
1.3. Contract Organization
The Contract Organization structure for Construction Phase is presented in Figure 1.1 and contact details of the key personnel are presented in Table 1.1 below:
Party |
Position |
Name |
Telephone no. |
Project Proponent (WSD) |
SE/CM2 |
Benny Lam |
2634-3573 |
Supervising Officer (Binnies Hong Kong Limited) |
Project Manager |
Christina Ko |
2608-7302 |
Chief Resident Engineer |
Roger Wu |
6343-1002 |
|
The Jardine Engineering Corporation, Limited, China State Construction Engineering (Hong Kong) Limited and Acciona Agua, S.A. Trading |
Project Manager |
Stephen Yeung |
2807-4665 |
Environmental Monitoring Manager |
Brian Kam |
9456-9541 |
|
Acuity Sustainability Consulting Limited |
Environmental Team Leader (ETL) |
Jacky Leung |
2698-6833 |
ANewR Consulting Limited |
Independent Environmental Checker (IEC) |
Louis Kwan |
2618-2831 |
1.4. Summary of Construction Works
The construction programme is presented in Appendix A. Detail of the major construction activities undertaken could be refer to Section 1.4 in each month EM&A Report.
The status for all environmental aspects is presented in Table 1.2.
Parameters |
Status |
Water Quality |
|
Baseline Monitoring under EM&A Manual |
The baseline water quality monitoring was conducted between 12 May 2020 to 6 Jun 2020 |
Impact Monitoring |
On-going |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
Impact Monitoring |
On-going |
Waste Management |
|
Mitigation Measures in Waste Management Plan |
On-going |
Environmental Audit |
|
Site Inspection covering Measures of Air Quality, Noise Impact, Water Quality, Waste, Ecological Quality, Fisheries, Landscape and Visual |
On-going |
Other than the EM&A work by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors.
The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Contract during the reporting period is provided in Appendix C.
2.1. Monitoring Requirements
To ensure no adverse noise impact, noise monitoring is recommended to be carried out within 300m radius from the nearby noise sensitive receivers (NSRs), during construction phase. The NSRs selected as monitoring station are (i) NSR4 - Creative Secondary School, (ii) NSR24 - PLK Laws Foundation College, and (iii) NSR31 - School of Continuing and Professional Studies - CUHK respectively.
2.2. Monitoring Locations
The monitoring locations were normally made at a point 1m from the exterior of the NSRs building façade and be at a position 1.2m above the ground. A correction of +3dB(A) was made to the free- field measurements.
According to the environmental findings detailed in the EIA report and Baseline Monitoring Report, the designated locations for the construction noise monitoring are listed in Table 2.1 below.
NSR ID |
Noise Sensitive Receivers |
Monitoring Location |
Position |
NSR 4 |
Creative Secondary School |
Roof Floor |
1 m from facade |
NSR 24 |
PLK Laws
Foundation College |
Pedestrian Road on Ground
Floor |
Free-field |
NSR 31 |
School of
Continuing and Professional Studies - CUHK |
Roof Floor |
1 m from facade |
Three noise monitoring locations for impact monitoring at the nearby sensitive receivers are shown in Figure 2.1-2.3.
|
Figure 2.1 NSR4
Creative Secondary School |
|
Figure 2.2
NSR24 PLK Laws
Foundation College |
|
Figure 2.3 NSR31
School of Continuing and Professional Studies
- CUHK |
2.3. Monitoring Parameter, frequency and duration
Construction noise level were measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 on normal weekdays. Table 2.2 summarizes the monitoring parameters, frequency and duration of the impact noise monitoring.
Time |
Duration |
Interval |
Parameters |
Daytime: 0700-1900 |
Day time: 0700-1900 (during normal weekdays) |
Continuously in Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq 30min L10 30min & L90 30min |
2.4. Impact Monitoring Methodology
The monitoring methodology and QA/QC procedure could be referring to Section 2.3 of the Monthly EM&A Report.
2.5.
Action and Limit
Levels
The Action/Limit Levels are in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) ¡§Noise from Construction Activities - Non-statutory Controls¡¨ and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [¡§EPD¡¨] under the Environmental Impact Assessment Ordinance, Cap 499,
S.16 are presented in Table 2.3.
Time Period |
Action |
Limit (dB(A)) |
0700-1900 on normal weekdays |
When one documented complaint is received from any one of the noise sensitive receivers |
- 70 dB(A) for school and - 65 dB(A) during examination period |
Notes: Limits specified
in the GW-TM and IND-TM
for construction and operation noise, respectively.
If exceedances were found during noise monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix E.
2.6.
Monitoring Results and Observations
Referring to EM&A manual Section 4.1.2, the impact noise monitoring should be carried out when there are Contract-related construction activities undertaken within a radius of 300m from the monitoring stations. No monitoring station was located within a radius of 300m of the Contract site as shown in Figure 2.4, no impact monitoring for noise impact was conducted in the reporting period.
In accordance with the recommendations of the EIA, water quality EM&A is required during dredging for the submarine pipelines and, during operation phase. In addition, baseline water quality monitoring was prior to the commencement of marine construction activities.
The following Section provides details of the water quality monitoring to be undertaken by the Environmental Team (ET) to verify the distance of sediment and brine plume dispersion and to identify whether the potential exists for any indirect impacts to occur to ecological sensitive receivers.
Water quality monitoring for the Contract can be divided into the following stages:
- Dredging activities during construction phase;
- Discharge of effluent from main disinfection during construction phase;
- Operation phase - first year upon commissioning; and,
- Continuous monitoring of effluent quality.
In addition, the marine works contractor is required to complete a silt curtain efficiency test for the combined use of floating silt curtain type and cage type silt curtain for dredging at seawater intake to confirm the silt curtain reduction efficiency assumptions of the assessment. The details of testing plan together with the silt curtain deployment plan shall be submitted by the ET to seek approval from the IEC and EPD.
3.1.
Water Quality Parameters
The parameters that have been selected for measurement in situ and in the laboratory are those that were either determined in the EIA to be those with the most potential to be affected by the construction works or are a standard check on water quality conditions. Parameters to be measured in the impact water quality monitoring are listed in Table 3.1.
Parameters |
Unit |
Abbreviation |
In-situ
measurements |
||
Dissolved oxygen |
mg/L |
DO |
Temperature |
oC |
- |
pH |
- |
- |
Turbidity |
NTU |
- |
Salinity |
0/00 |
- |
Total Residual Chlorine NOTE1 |
mg/L |
TRC |
Laboratory measurements |
||
Suspended Solids |
mg/L |
SS |
Iron-Soluble |
mg/L |
Fe |
Anti-scalant as Reactive Phosphorus |
mg/L |
PO4 as P- |
NOTE 1: Monitoring of TRC will be conducted when cleaning and sterilization of the new freshwater main is carried
out.
In addition to the water quality parameters, other relevant data was measured and recorded in Water Quality Monitoring Logs, including the location of the sampling stations, water depth, time, weather conditions, sea conditions, tidal stage, current direction and velocity, special phenomena and work activities undertaken around the monitoring and works area that may influence the monitoring results.
3.2. Monitoring Equipment
The monitoring methodology, monitoring equipment and QA/QC procedure could be referring to Section 3.1.2 - 3.1.4 of the Monthly EM&A Report.
3.3. Monitoring Location
The impact water quality monitoring locations are in accordance with the EM&A Manual and detailed in Table 3.3 below.
Station |
Easting |
Northing |
Description |
CE |
843550 |
815243 |
Upstream control station at ebb tide |
CF |
846843 |
810193 |
Upstream control station at flood tide |
WSR1 |
846864 |
812014 |
Ecological sensitive receiver at Tung Lung Chau |
WSR2 |
847645 |
812993 |
Fisheries sensitive receiver at Tung Lung Chau |
WSR3 |
848023 |
813262 |
Ecological sensitive receiver at Tung Lung Chau |
WSR4 |
847886 |
814154 |
Ecological sensitive receiver at Tai Miu Wan |
WSR16 |
845039 |
815287 |
Ecological sensitive receiver at Fat Tong Chau |
WSR33 |
847159 |
814488 |
Ecological sensitive receiver at Tai Miu Wan |
WSR36 |
846878 |
814081 |
Ecological sensitive receiver at Kwun Tsai |
WSR37 |
846655 |
813810 |
Ecological sensitive receiver at Tit Cham Chau |
NF1 |
846542 |
813614 |
Edge of mixing zone, ~ 200m west of outfall diffuser |
NF2 |
846942 |
813614 |
Edge of mixing zone, ~ 200m east of outfall diffuser |
NF3 |
846742 |
813414 |
Edge of mixing zone, ~ 200m south of outfall diffuser |
WSR1 to WSR37 were identified in accordance with Annex 14 of the EIAO-TM as well as Clause
3.4.4.2 of the Environmental Impact Assessment Study Brief for Desalination Plant at Tseung Kwan O (No. ESB-266/2013). WSR1 to WSR3 are sited near the Tung Lung Chau Fish Culture Zone; WSR16 and WSR36 are sited near the coral assemblages along the coastlines of Fat Tong Chau and Kwun Tsai respectively; WSR 4 and WSR33 are sited near the Coastal Protection Area and coral assemblages in waters of Tai Miu Wan; WSR37 is sited near the fisheries resource including spawning and nursery grounds at the coastal water of Tit Cham Chau.
3.4. Action and Limit levels
The Action and Limit Levels have been set based on the derivation criteria specified in the EM&A Manual. Based on the baseline water quality monitoring data and the derivation criteria, the Action/Limit Levels have been derived and are presented in Table 3.4.
Parameters |
Action |
Limit |
|
Construction Phase Impact
Monitoring |
|||
DO in mg/L |
Surface and Middle |
Surface and Middle |
|
|
7.30 mg L-1 |
4 mg L-1 |
|
|
Bottom |
Bottom |
|
|
7.31 mg L-1 |
2 mg L-1 |
|
|
Tung Lung Chau Fish Culture Zone |
Tung Lung Chau Fish Culture Zone |
|
|
5.1 mgL-1 or level at control station |
5.0 mgL-1 or level at control station |
|
|
(whichever the lower) |
(whichever the lower) |
|
SS in |
mg/L |
5.00 mg L-1 or 20% exceedance of |
6.00 mg L-1 or 30% exceedance of |
(Depth- |
|
value at any impact station |
value at any impact station compared |
averaged) |
|
compared with corresponding data |
with corresponding data from |
|
|
from control station |
control station |
Turbidity in NTU |
2.41 NTU or 20% exceedance of |
2.84 NTU or 30% exceedance of |
|
(Depth- |
value at any impact station |
value at any impact station compared |
|
averaged) |
compared with corresponding data |
with corresponding data from |
|
|
from control station |
control station |
|
First-year Operation Phase
Monitoring iv |
|||
DO in mg/L |
Surface and Middle |
Surface and Middle |
|
|
7.30 mg L-1 |
4 mg L-1 |
|
|
Bottom |
Bottom |
|
|
7.31 mg L-1 |
2 mg L-1 |
|
|
Tung Lung Chau Fish Culture Zone |
Tung Lung Chau Fish Culture Zone |
|
|
5.1 mgL-1 or level at control station |
5.0 mgL-1 or level at control station |
|
|
(whichever the lower) |
(whichever the lower) |
SS in mg/L (Depth- averaged) |
5.00 mg L-1 or 20% exceedance of valueat any impact station compared with corresponding data from control station |
6.00 mg L-1 or 30% exceedance of value at any impact station compared with corresponding data from control station |
Turbidity in NTU (Depth- averaged) |
2.41 NTU or 20% exceedance of value at any impact station compared with corresponding data from control station |
2.84 NTU or 30% exceedance of value at any impact station compared with corresponding data from control station |
Salinity in PSU (Depth- averaged) |
34.28 PSU or 9% exceedance of value at any impact station compared with corresponding data from control station |
34.60 PSU or 10% exceedance of value at any impact station compared with corresponding data from control station |
Iron in mg/L (Depth- averaged) |
0.3 mgL-1 |
0.3 mgL-1 |
Notes:
i.
"Depth-averaged" is calculated by taking the arithmetic means of reading
of all three depths.
ii. For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits.
iii. For Turbidity, SS, iron and Salinity, non-compliance of the water quality limits
occurs when monitoring result is higher
than the limits.
iv. For the Action and Limit Levels adopted during
First-year Operation Phase Monitoring, further
review would be made according to the EM&A Manual during
Operation Phase.
3.5. Monitoring Programme
No marine water quality monitoring was conducted between March 2020 to February 2021. Marine construction works and dredging activities for the Project were commencement in March 2021 and April 2021 respectively.
The ET of the Contract had conducted the impact water quality monitoring between 1 March 2021 to 31 March 2021 at the ten designated monitoring stations and the six designated monitoring at waters near TKO in accordance with the EM&A Manual and Contract Specification respectively.
3.6. Monitoring results and observations
The impact water quality monitoring at the designated locations were conducted by the ET as scheduled in the reporting period. The graphical presentation of the water quality monitoring result was shown in Appendix D.
Six (6) of the general water quality monitoring results of SS obtained had exceeded the Action level. One (1) of the general water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.
Details of the exceedance could be referring to Appendix O of the Monthly EM&A Report.
The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. Details of cumulative waste management data are presented as a waste flow table in Appendix F.
5.1. Monitoring Requirement
In according with Section 11 of the EM&A Manual, monitoring of landfill gas is required for construction works within the 250m Consultation Zone. Part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone; and part of the 1,200 mm diameter fresh water mains along Wan Po Road falls within the SENT Landfill and SENT Landfill Extension Consultation Zones, TKO Stage II/III Restored Landfill and TKO Stage I Restored Landfill Consultation Zones.
For the part of the desalination plant and the indicative area of natural slope mitigation works fall within the SENT Landfill Extension Consultation Zone in this contract, since the SENT Landfill Extension is still under construction, the Landfill gas monitoring will be conducted after the commencement of operation of the SENT Landfill Extension which will be 2021 Quarter 3 according to the latest construction programme shown in the monthly EM&A Report of SENT Landfill Extension. The Contractor¡¦s safety officer will keep review the necessity of landfill gas monitoring during the construction stage. No landfill gas monitoring was conducted in the reporting period.
The Environmental Complaint Handling Procedure is shown in below Figure 6.1:
No noise monitoring was conducted during the reporting period since there are no Contract- related construction activities undertaken within a radius of 300m from the monitoring locations.
No marine water quality monitoring was conducted between March 2020 to Feb 2021. Marine construction works and dredging activities for the Project were commencement in March and April 2021 respectively.
Six (6) of the general water quality monitoring results of SS obtained had exceeded the Action level. One (1) of the general water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level.
Details of the exceedance could be referring to Appendix O of the represent Monthly Report. No landfill gas monitoring was conducted during the reporting period.
No notification of summons and prosecution was received in the reporting period. Statistics on complaint
and regulatory compliance are summarized in Appendix
J.
Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, site inspections were carried out from March 2020 to March 2021.
Fifty-five site inspection were carried out in the reporting period.
Environmental deficiencies were observed during weekly site inspection. Key observations during the site inspections and during the reporting period could be referring to the represent Monthly Report.
According to the EIA Study Report,
Environmental Permit, contract
documents and EM&A
Manual, the mitigation measures detailed in the documents should be
implemented as much as practical during the reporting period. An updated
Implementation Status of Environmental Mitigation Measures (EMIS) is provided
in Appendix C.
This is the 1st Annual EM&A Review Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 16 March 2020 to 31 March 2021, in accordance with the EM&A Manual and the requirement under FEP-01/503/2015/A.
No noise monitoring was conducted in the reporting period due to the over distant monitoring station from the works location, in which construction activities were not undertaken within a radius of 300m from the monitoring locations.
The EM&A works for water quality were conducted during the reporting period in accordance with the EM&A Manual.
Six (6) of the general water quality monitoring results of SS obtained had exceeded the Action level. One (1) of the general water quality monitoring results of SS obtained during the reporting period had exceeded the Limit Level. All Action and Limit Level exceedances were unrelated to the project.
Details of the exceedance could be referring to Appendix O of the represent Monthly EM&A Report.
No landfill gas monitoring was conducted in the reporting period.
Weekly environmental site inspection was conducted during the reporting period. Minor deficiency was observed during site inspection. The environmental performance of the project was therefore considered satisfactory.
According to the environmental site inspections performed in the reporting month, the Contractor is reminded to pay attention on maintaining proper materials storage, site tidiness and dust suppression mitigation measures.
No environmental complaint was received in the reporting period.
No notification of summons or prosecution was received since commencement of the Contract.
The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
Appendix A
Master Programme
Appendix B
Overview of Desalination Plant in Tseung Kwan O
Appendix C
Summary of Implementation Status of
Environmental Mitigation
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Air Quality |
|
|||||||
S4.8.1 |
Impervious dust screen
or sheeting will be provided to enclose scaffolding from the ground
floor level of building for construction of superstructure of the
new buildings. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction
Dust) |
S4.8.1 |
Impervious sheet will
be provided for
skip hoist for material transport. |
Land site/ During Construction, particularly dry season |
Contractor(s) |
|
ü |
|
NA |
|
S4.8.1 |
The area where dusty
work takes place
should be sprayed with water
or a dust suppression chemical immediately prior to, during and
immediately after dusty activities
as far as practicable. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
All dusty materials should
be sprayed with water or a dust suppression chemical immediately
prior to any loading,
unloading or transfer operation. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
Dropping
heights for excavated materials should be controlled to a practical height to minimize the fugitive dust arising from
unloading. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
During transportation by truck, materials should not be loaded to a
level higher than the side and tail
boards, and should be dampened or covered before transport. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
Wheel washing device should be provided at the exits of the work
sites. Immediately before leaving a
construction site, every vehicle shall be washed
to remove any dusty material from its body and wheels as far as practicable. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
Road sections between
vehicle-wash areas and vehicular entrance will be paved. |
Land site/ During Construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
Hoarding of not less than 2.4m high from ground level will be provided along the length of the Project Site
boundary. |
Land site/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
|
S4.8.1 |
Haul
roads will be kept clear of dusty materials and will be sprayed with water so as to maintain the entire road
surface wet at all times. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after reminder |
|
EIA Reference |
Recommended Environmental Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns
to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S4.8.1 |
Temporary stockpiles of dusty materials will be either
covered entirely by impervious sheets
or sprayed with water to maintain the entire surface
wet all the time. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after reminder |
|
S4.8.1 |
Stockpiles of more than 20 bags of cement, dry pulverised fuel ash and dusty construction
materials will be covered entirely by impervious sheeting sheltered on top and 3-sides. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after
observation and reminder |
|
S4.8.1 |
All exposed areas
will be kept
wet always to minimise dust emission. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
Ultra-low-sulphur diesel (ULSD) will be used for all construction plant on- site,
as defined as diesel
fuel containing not more
than 0.005% sulphur by weight) as
stipulated in Environment, Transport and Works Bureau Technical Circular (ETWB-TC(W)) No 19/2005 on Environmental Management on Construction Sites. |
Land site/ During construction/ During Operation |
Contractor(s) |
|
ü |
ü |
Implemented |
Environment, Transport and Works Bureau Technical Circular (ETWB- TC(W)) No 19/2005 on Environmental Management on |
S4.8.1 |
The engine of the construction equipment during idling will be switched off. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.8.1 |
Concrete batching plant will be required on site. control measures recommended in the Guidance Note on a Best Practicable
Means for Cement
Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. The control measures recommended in the Guidance Note on a Best Practicable Means for Cement
Works (Concrete Batching Plant) (BPM 3/2 (93)) will be implemented. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S4.8.1 |
Regular maintenance of
construction equipment deployed on-site will be conducted to prevent black smoke emission. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
|
S4.10 |
To ensure proper implementation of the recommended dust mitigation measures and good construction site
practices during the construction phase,
environmental site audits on weekly basis is recommended throughout the construction period. |
Land site/ During construction |
Contractor(s)/ ET &
IEC |
|
ü |
|
Implemented |
|
Note: D - Design
stage C - Construction O - Operation
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementatio n Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Noise |
||||||||
S5.7 |
Only well-maintained plant will
be operated on-site
and plant will
be serviced regularly during
the construction phase. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Silencers or mufflers on
construction equipment will be utilised and will be properly maintained during the
construction phase. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Mobile plant, if any, will be sited
as far away
from NSRs as possible. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Machines and plant (such as trucks) that may be in intermittent use will be shut down between work periods or will be throttled down
to a minimum. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction
Works |
S5.7 |
Plants known to emit noise strongly in one
direction will, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction
Works |
S5.7 |
Material stockpiles and other structures will be effectively utilised, wherever
practicable, in screening noise from on-site construction activities. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise
from Construction Works |
S5.7 |
Use of Quite
Powered Mechanical Equipment (QPME). |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction
Works |
S5.7 |
Movable noise barriers of 3m in height with skid footing should be
used and located within a few metres of stationary plant
and mobile plant
such that the line of sight to the NSR is blocked
by the barriers. The length of the barrier should be at least five times
greater than its height. The noise barrier
material should have a superficial surface density of at least 7 kg m-2 and have no o or gappeningss. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction
Works, |
S5.7 |
The
noise insulating sheet should be deployed
such that there would be no opening or gaps on the joints. |
Noise control/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise
from Construction Works, |
S5.7 |
Construction activities (e.g.
excavation/shoring, reinstatement (asphalt), and pipe jacking) will be planned and carried out in sequence,
such that items of PME proposed for these activities will not be operated simultaneously. |
Noise control/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
A Practical Guide for the Reduction of Noise from Construction
Works |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementatio n Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S5.7 |
PMEs will not be used at the works areas near educational institutions with residual impact (ie the
¡§influence area¡¨ within a radius of 40m) during school hours in order to reduce impact to the educational
institutions. |
Noise control
/ During construction |
Contractor(s) |
|
ü |
|
N/A |
A Practical Guide for the Reduction of Noise from Construction Works |
S5.7 |
Noise enclosures or acoustic sheds
would be used to cover
stationary PME such as generators. Portable/Movable noise
enclosure made of material with
superficial surface density
of at least 7 kg m-2 may be used for screening the noise from operation of the saw/groover, concrete. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
|
S5.9 |
Sawcutting
pavement, breaking up of pavement, excavation /shoring, pipe laying, backfilling, reinstatement (concrete) and pipe jacking shall
be scheduled outside the
examination period. |
Noise control/
Pre- construction/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
|
S5.9 |
In view the duration of noise exceedance at Creative Secondary
School, PLK Laws Foundation College, TKO Kei Tak Primary
School and School
of Continuing and
Professional Studies-CUHK is limited to 8 weeks, the construction work in the influence areas near the four schools
shall be scheduled during long school holidays (eg
summer holiday, Easter holiday or Christmas holiday, etc) as far as practicable. Scheduling the construction work for the four schools. |
Noise control/ Pre- construction/ During construction |
Contractor(s) |
ü |
ü |
|
N/A |
|
S5.10 |
A noise
monitoring programme shall be implemented for the construction phase. |
Designated monitoring stations as defined in EM&A Manual/During construction phase |
ET |
|
ü |
|
N/A |
|
S5.10 |
The effectiveness of on-site control measures could also
be evaluated through the regular site audits. |
All facilities/ During construction |
Contractor(s)/ ET & IEC |
|
ü |
|
Implemented |
- |
Note: D - Design
stage C - Construction O - Operation
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Water Quality |
||||||||
S6.9 |
Dredged marine sediment will be disposed of in a gazetted
marine disposal area in accordance
with marine dumping permit conditions of the
Dumping at Sea Ordinance (DASO). |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Dumping at Sea Ordinance (DASO) |
S6.9 |
Disposal vessels
will be fitted
with tight bottom
seals in order
to prevent leakage of material during transport. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
Barges will be filled to a level,
which ensures that material does not spill
over during transport to the disposal site and that
adequate freeboard is maintained
to ensure that the decks are not washed by
wave action. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
After dredging, any excess materials will be cleaned
from decks and exposed
fittings before the vessel is moved
from the dredging area. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
All
vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
All vessels must have
a clean ballast system. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
No discharge of sewage/grey wastewater should be allowed. Waste water from potentially contaminated area on working vessels should be minimized and collected. These kinds
of wastewater should
be brought back to port and discharged at
appropriate collection and
treatment system. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
No soil waste is allowed to be disposed overboard. |
Marine Dredging/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S6.9 |
Silt removal
facilities such as silt
traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the requirements of the TM standard under the WPCO. The design
of silt removal facilities will be based on the guidelines provided in ProPECC
PN 1/94. All drainage facilities and
erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit
will be removed regularly. |
Land site &
drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after
observation and reminder |
ProPECC PN 1/94
TM Standard under the WPCO |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
Earthworks to form
the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms. |
Land site & drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
Appropriate surface
drainage will be designed and provided where
necessary. |
Land site &
drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
The precautions to be taken at any time of year when rainstorms are likely together with the actions to be
taken when a rainstorm is imminent or forecasted and
actions to be taken during
or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. |
Land site &
drainage/ During construction |
Contractor(s) |
ü |
ü |
|
Implemented |
ProPECC PN 1/94 |
S6.9 |
Oil interceptors will be provided in the drainage system where necessary and regularly emptied
to prevent the release of oil and grease into the storm water drainage system
after accidental spillages. |
Land site &
drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after reminder |
- |
S6.9 |
Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge, if any,
will be adequately designed for the controlled
release of storm flows. |
Land site &
drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 |
The temporary diverted drainage, if any, will be reinstated to the original condition when the construction work has finished or when the temporary
diversion is no longer required. |
Land site &
drainage/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S6.9 |
Appropriate numbers of portable toilets shall be provided by a licensed contractor to serve
the construction workers
over the construction site to prevent
direct disposal of sewage into the water environment. |
Land site &
drainage/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S6.9 and S6.12 |
The sterilization water should be dechlorinated with total residual chlorine (TRC) level below
1 mg/L before
discharge to public
sewer. In situ testing of TRC should also be
conducted for the discharge of chlorinated
water for pipeline disinfection to ensure sufficient dechlorination before discharge to
public sewer. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
|
ü |
ü |
N/A |
Technical Memorandum for Effluents Discharged into
Drainage and Sewerage Systems
Inland and Coastal Waters |
S6.9 |
The cleaning and flushing water should also be treated and desilted
to the relevant discharge
requirement stipulated in TM-DSS before discharging. |
Sterilization of water mains prior to commissioning |
Contractor(s) |
|
ü |
ü |
N/A |
Technical Memorandum for Effluents Discharged into
Drainage and Sewerage Systems
Inland and Coastal Waters |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S6.9 |
Site drainage should be well maintained and good construction practices should be observed to ensure that oil, fuels,
solvents and other
chemicals are managed, stored
and handled properly and do not enter the nearby water
streams. |
Land site &
drainage/ During construction/ During operation |
Contractor(s) |
|
ü |
ü |
Implemented, rectified after
reminder |
- |
S6.12 |
Regular site inspections will be carried out in order to confirm that regulatory requirements are being met and that contractors are implementing the
standard site practice and mitigation measures as proposed to reduce potential impacts to water
quality. |
During construction |
Contractor(s)/ ET & IEC |
|
ü |
|
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Waste Management |
||||||||
S8.5 |
Nomination
of approved personnel to be responsible for standard site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes
generated at the site. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Training of site personnel in proper waste management and chemical handling
procedures. Training will be
provided to workers on the concepts
of site cleanliness and appropriate waste management procedures, including waste
reduction, reuse and recycling at the beginning of the construction works. |
Contract mobilization/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Provision of sufficient
waste disposal points and regular
collection for disposal. |
All area/ During construction/ During operation |
Contractor(s) |
|
ü |
ü |
Implemented, rectified after
observation |
DEVB TC(W)
No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
Appropriate measures to reduce windblown litter and dust transportation
of waste by either covering trucks or
by transporting wastes in enclosed
containers. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W)
No. 8/2010, Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
A waste management plan (WMP) as stated in the ¡§ETWB TC(W) No. 19/2005, Environmental Management on
Construction Sites¡¨ for the amount
of waste generated, recycled and
disposed of (including the disposal
sites) will be established and implemented
during the construction
phase as part of the Environmental
Management Plan (EMP). The Contractor will be required to prepare the EMP and submits it to the Architect/ Engineer under the Contract for approval prior
to implementation. |
All area/
During construction |
Contractor(s) |
|
ü |
|
Implemented |
ETWB TC(W)
No. 19/2005, Environmental Management on Construction Sites |
S8.5 |
Separation of chemical wastes
for special handling and appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
N/A |
Chapters 2 & 3 Code of Practice on the Packaging, Labelling & Storage
of Chemical Wastes published under the Waste
Disposal Ordinance (Cap 354), Section 35 |
S8.5 |
Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after
reminder |
Waste Disposal Ordinance (Cap 354) |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
A recording system for the amount of wastes generated/ recycled and disposal
sites. The trip- ticket system will be included as one of
the contractual requirements and implemented by the
contractor(s). |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W)
No. 6/2010, Trip Ticket System for Disposal of Construction & Demolition Materials |
S8.5 |
Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance
reuse or recycling of material and their proper disposal. |
Land site/ During construction/ During operation |
Contractor(s) |
|
ü |
|
Implemented |
WBTC 32/92, The Use of Tropical
Hard Wood on Construction Site |
S8.5 |
Encourage collection of aluminium cans and
waste paper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
ETWB TCW No. 33/2002, Management
of Construction and Demolition Material Including Rock |
S8.5 |
Any unused
chemicals and those
with remaining functional capacity will be recycled as far as possible. |
Land site/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S8.5 |
Use of reusable non-timber formwork to reduce
the amount of C&D materials. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
WBTC 32/92, The Use of Tropical
Hard Wood on Construction Site |
S8.5 |
Prior to disposal of construction waste,
wood, steel and other metals
will be separated to the extent practical, for
re-use and/or
recycling to reduce the quantity
of waste to be disposed of to landfill. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W)
No. 6/2010, Trip Ticket
System for Disposal of Construction & Demolition Materials |
S8.5 |
Proper
storage and site practices to reduce the potential for damage
or contamination of construction materials. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after
observation and reminder |
- |
S8.5 |
Plan and stock construction materials carefully to reduce amount
of waste generated and avoid unnecessary generation of waste. |
All areas/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
A Sediment Quality Report (SQR) for sampling and chemical testing of the sediment will be prepared and submitted to the EPD for approval. The approved detailed sampling and chemical testing
will be carried out prior to the commencement of the
dredging activities to confirm the sediment disposal method. |
Marine works/ During construction |
Contractor(s) |
|
ü |
|
N/A |
ETWB TC(W)
No. 34/2002 and Dumping at Sea Ordinance (DASO) |
S8.5 |
The management of dredged/ excavated sediment management requirement from ETWB TC(W) No. 34/2002 will be incorporated in the |
Marine works/ During construction |
WSD/ Contractor(s) |
|
ü |
|
Implemented |
ETWB TC(W)
No. 34/2002 and
Dumping |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
Specification of the Contract Documents. |
|
|
|
|
|
|
at Sea
Ordinance (DASO) |
S8.5 |
The contractor will open a billing account with EPD in
accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation for the payment of disposal charges. |
Contract mobilisation/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
Cap 354N
Waste Disposal (Charges for Disposal of Construction Waste) Regulation |
S8.5 |
A trip-ticket system
will be established in accordance with DEVB TC(W)
No. 6/2010 to monitor
the reuse of surplus excavated materials off-site and disposal of construction waste and general refuse at transfer facilities/ landfills, and to control
fly-tipping. |
Contract mobilisation/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
DEVB TC(W) No. 6/2010, Trip Ticket System
for Disposal of Construction
& Demolition Materials |
S8.5 |
The project proponent will
also conduct regular
inspection of the waste management measures implemented on site as described in the
Waste Management Plan. |
All area/
During construction |
Contractor(s)/ ET/ IEC |
|
ü |
|
Implemented |
ETWB TC(W)
No. 19/2005, Environmental Management on Construction Sites |
S8.5 |
A recording system
(similar to summary table as shown
in Annex 5 and Annex 6 of
Appendix G of ETWB TC(W)
No. 19/2005) for the
amount of waste generated, recycled and disposed of (including the
disposal sites) will be established during the construction phase. |
All area/
During construction |
Contractor(s) |
|
ü |
|
Implemented |
Annex 5 and
Annex 6 of Appendix
G of ETWB TC(W) No. 19/2005 |
S8.5 |
Inert C&D materials (public fill) will be reused
within the Project
as far as practicable. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
Public fill and construction waste shall be segregated and stored in different containers or skips to facilitate reuse
or recycling of materials and their proper disposal. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented, rectified after
reminder |
- |
S8.5 |
Specific areas of the work site will be designated for such segregation and storage if immediate use is not practicable. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
To reduce the potential dust
and water quality impacts of site formation works,
C&D materials will
be wetted as quickly as possible to the extent
practice after filling. |
All area/
During construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control (Construction Dust) Regulation (Cap 311R); WPCO (Cap 358) |
S8.5 |
Open
stockpiles of excavated/ fill
materials or construction wastes
on- site should be covered with tarpaulin or similar fabric. |
Land site/ During Construction, particularly dry season |
Contractor(s) |
|
ü |
|
Implemented, rectified after
observation |
Air Pollution Control (Construction Dust) Regulation (Cap 311R) |
S8.5 |
Chemical waste container shall be suitable
for the substance they are |
All area/ During |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste Disposal |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
holding, resistant to corrosion, maintained in a good
condition, and securely closed. |
construction/ During operation |
|
|
|
|
|
(Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Chemical waste
container shall have a capacity of less than
450 L unless the
specifications have been approved
by the EPD. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
A label in English and Chinese shall be displayed on the chemical container in accordance with instructions prescribed in Schedule 2 of the Regulations. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Storage areas for chemical waste
shall be enclosed on at least
3 sides. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Storage areas for chemical waste shall have an impermeable floor and bunding, of capacity to accommodate 110%
of the volume
of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest. |
All
area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Storage areas for chemical waste
shall have adequate ventilation. |
All area/ During |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste Disposal |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
|
construction/ During operation |
|
|
|
|
|
(Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Storage areas for chemical waste shall be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary). |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Storage areas
for chemical waste
shall be arranged so that incompatible materials are appropriately
separated. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
General refuse
will be stored
in enclosed bins
or compaction units
separately from construction and chemical
wastes. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented, reminder issued. |
Waste
Disposal (Chemical Waste)
(General) Regulation; Code of Practice on the Packaging, Handling and Storage of Chemical Wastes |
S8.5 |
Adequate number of waste
containers will be provided to
avoid over- spillage of waste. |
All
area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
DEVB TC(W) No. 8/2010 Enhanced Specification for Site Cleanliness and Tidiness. |
S8.5 |
A reputable waste collector will be employed by the Contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis
to minimise odour, pest
and litter impacts. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
- |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S8.5 |
Recycling bins will be provided at strategic locations within
the Site to facilitate recovery of
recyclable materials (including aluminium can, waste
paper, glass bottles and plastic
bottles) from the Site. Materials recovered will be sold
for recycling. |
All area/ During construction/ During operation |
Contractor(s)/ WSD |
|
ü |
ü |
Implemented |
- |
S8.5 |
To avoid any odour and litter
impact, accurate number
of portable toilets will be provided for workers on-site. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S8.5 |
The burning of refuse on construction sites
is prohibited by law. |
All area/ During
construction |
Contractor(s) |
|
ü |
|
Implemented |
Air Pollution Control Ordinance (Cap
311) |
S8.7 |
To facilitate monitoring and control over the contractors¡¦ performance on waste
management, a waste
inspection and audit
programme
will be implemented throughout the construction
phase. |
All facilities/ During construction |
ET/ IEC |
|
ü |
|
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
Ecology |
||||||||
S9.7 |
For slope mitigation works
within the Clear Water Bay Country Park, to avoid tree felling and damages to trees, the
exact locations of the flexible barrier foundation
plates, soil nails and rock dowels can be adjusted during detailed design, and a setback distance from existing trees is recommended to be maintained as far as practical. A detailed specification
describing the exact locations of the flexible
barrier foundation plates,
soil nails and rock dowels
will be prepared to illustrate how the setback
distance from existing trees would be implemented for tree avoidance. |
Slope mitigation works area/ During
detailed design/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S9.7 |
Pruning of tree canopies along the alignment of the flexible barriers shall be limited to a minimum. |
Slope mitigation works area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
|
S9.7 |
The alignment of flexible barriers shall be optimized to preserve all species of conservation interest and minimize the impact to the existing vegetation as far as practicable. All individuals of Marsdenia lachnostoma within the slope mitigation areas shall be retained in- situ, by positioning the alignment of flexible barrier at a
minimum 1.5m in a radius
away from these individuals. |
Slope mitigation works area/ During
detailed design/ During
construction |
Contractor(s) |
ü |
ü |
|
N/A |
- |
S9.7 and 9.10 |
At the detailed design stage prior to the commencement of the slope mitigation
works, a vegetation survey shall be
carried out at the slope mitigation
areas within the Clear Water Bay Country Park
to assess the condition and identify
the location of each individual of Marsdenia lachnostoma and other
flora species of conservation interest that may be directly affected by the construction works. |
Slope mitigation works area/ During
detailed design/ During
construction |
Contractor(s) |
ü |
|
|
Implemented |
- |
S9.7 |
Temporary fencing will be installed to fence off the concerned species either in groups of individually within the works area and in the close proximity to prevent
from being damaged and disturbed during construction. A sign identifying the site shall
be attached to the fence
and flagging tape
shall be attached to the individuals to visualize their locations. |
Slope mitigation works area/ During
construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 and S9.10 |
A specification for fencing
and demarcating individuals of Marsdenai lachnostoma (or other
flora species of conservation interest, if found) adjacent to the proposed alignment of the flexible barriers will be prepared to protect the species. |
Slope mitigation works area/ During
construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
Induction training shall
also be provided to all site
personnel in order
to brief them on this flora of conservation interest including the locations |
Slope mitigation works area/ During |
Contractor(s) |
|
ü |
|
N/A |
- |
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives
of the recommended measures
& main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
and their importance. |
construction |
|
|
|
|
|
|
S9.7 |
The resident site
supervisory staff will closely monitor the conditions of concerned individuals during construction of flexible barriers in the close
proximity. |
Slope mitigation works area/ During
construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
Erect fences
along the boundary of the works
area before the commencement of works to prevent vehicle movements and encroachment of personnel onto adjacent areas. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Regularly check the work site boundaries to ensure that they are not breached and that damage does not occur to surrounding areas. |
All area/ During construction |
Contractor(s)/ Environmental Team (ET) |
|
ü |
|
Implemented. |
- |
S9.7 |
Avoid any damage and disturbance, particularly those caused by filling and illegal
dumping, to the surrounding habitats through proper management of waste disposal. |
All area/ During construction |
Contractor(s) |
|
ü |
|
Implemented |
- |
S9.7 |
Reinstate
temporarily affected areas, particularly the
habitats of plantation and
shrubland-grassland immediately
after completion of construction works,
through on-site tree/shrub planting. The tree/shrub species will be chosen with reference to those in the surrounding area. |
All area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
S9.7 |
Affected habitats within the Clear
Water Bay Country
Bay shall be reinstated by hydro-seeding and planting of climbers and native shrub seedlings where practical upon completion
of the slope mitigation works. |
All area/ During construction |
Contractor(s) |
|
ü |
|
N/A |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
Landscape & Visual |
|||||||
S11.10 & 11.11 |
The construction area
and area allowed
for temporary structures, such as the contractor¡¦s office, will be minimized to a practical minimum. (MM1) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
At the detailed design stage, the design team will seek to
minimize the landscape footprint of the Project
and above ground
facilities, while satisfying all other
requirements. (MM2) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
Design principles will be adopted to take into
account the surrounding area,
particularly Clear Water Bay Country Park behind and the nearby waterfront, with due consideration given
to: - green roofs
where practical (i.e.
without equipment on the roof); - roadside planting; - aesthetic treatment of all structures; - vertical greening; - screen planting along application site;
and - landscape
enhancement with amenity planting where practical including planting along the edge (site boundary) fence with
native shrubs where
feasible, to reduce
their visual impact
and blend them
into the surrounding landscape. (MM3) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S11.10 & 11.11 |
All trees within
the Project Site or the potential slope mitigation works area will be
carefully protected during construction according to DEVB TCW No. 10/2013 - Tree Preservation
(MM4) |
All area/ Detailed design/
During construction/ During
operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
ETWB TCW No. 3/2006
- Tree Preservation. |
S11.10 & 11.11 |
No tree within the Country Park will be felled. Trees within the Site unavoidably affected by the works will
be transplanted where necessary and practical. For
trees that need to be felled, compensatory planting will be provided to the satisfaction of
relevant Government departments. A compensatory tree planting proposal including locations of tree compensation will be submitted to seek
relevant government department¡¦s
approval, in accordance with DEVB TC(W) No. 10/2013. (MM5) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
DEVB TC(W)
No. 10/2013 |
S11.10 & 11.11 |
Any slope mitigation works necessary to address natural
terrain hazards, will
be minimized to minimize any potential environmental impact to the Country Park
e.g. soil nailing and rock stabilization will aim to avoid existing trees e.g. should any restoration of vegetation be necessary, the |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
N/A |
|
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
best planting matrix
with native species
will be established, with the aim of resembling the existing vegetation. (MM6) |
|
|
|
|
|
|
|
S11.10 & 11.11 |
Dredging works for the installation of intake structures and outfall diffusers should be minimized to avoid
or reduce any potential environmental impacts
to as low
as reasonably practicable (ALARP). The intake
and outfall structures (e.g. intake openings and diffuser heads)
will be prefabricated and transferred to site for installation. (MM7) |
All area/
Detailed design/ During
construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S11.10 & 11.11 |
All night-time lighting will
be reduced to a practical minimum both in terms of number of level and will be hooded and directional. (MM8)
units and lux level
and will be hooded and directional. (MM8) |
All area/ Detailed design/ During construction/ During operation |
WSD/ Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
Note: D - Design stage C - Construction O - Operation
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
|
Landfill Gas Hazard |
|||||||
S12.7 |
During all works, safety procedures should be implemented to minimise the
risks of fires and explosions, asphyxiation of workers and toxicity effects resulting from contact with
contaminated soil and groundwater. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
- |
S12.7 |
During trenching and excavation as well as creation of confined
spaces at near to or below
ground level, precautions should be clearly
laid down and rigidly Gas detection equipment and appropriate breathing apparatus should be available
and used when entering confined spaces or trenches deeper than 1 metre. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
The Contractor should
make the workers are aware of potential hazards
of working in confined
spaces (any chamber, manhole or culvert which is large enough to permit access
to personnel). Such work in confined spaces
is controlled by the Factories and Industrial Undertakings (Confined Spaces) Regulations of the Factories and
Industrial Undertakings Ordinance.
Following the Safety Guide to Working in Confined Spaces ensures compliance with the above
regulations. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Safety officers, specifically trained with regard to landfill gas and leachate related hazards and the appropriate actions to take in adverse circumstances, should be present on the
site throughout the works, in particular,
when works are undertaken below grade. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
All personnel who work on
site and all visitors to the
site should be made aware of the
possibility of ignition of gas in the vicinity of the works, the possible presence of contaminated water
and the need to avoid physical contact
with it. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Monitoring for landfill gas should be undertaken in all excavations, manholes, chambers (particularly during
pipe jacking) and any confined spaces through
the use of an intrinsically safe portable instrument, appropriately
calibrated and capable of measuring the concentrations of methane. carbon dioxide and oxygen. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Monitoring frequency and areas to be monitored should be specified prior to
commencement of groundwork, either by the Safety Officer, or by an appropriately qualified person. All measurements should
be recorded and documented. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
EIA Reference |
Recommended Environmental
Protection Measures/ Mitigation Measures |
Objectives of the
recommended measures & main concerns to address |
Implementation Agent |
Implementation Stage |
Implementation Status |
Relevant Legislation & Guidelines |
||
D |
C |
O |
||||||
S12.7 |
Proceed drilling with
adequate care and
precautions against the potential hazards which may be encountered. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Prior to the commencement of the site works, the drilling contractor should devise a 'method-of- working'
statement covering all normal and emergency procedures (including but not limited to number of operatives, experience and special skills of
operatives, normal method of operations, emergency
procedures, supervisors responsibilities, storage
and use of safety equipment, safety
procedures and signs, barriers and guarding). The site supervisor and all
operatives must be familiar with this statement. |
All
area/ During construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
Where below ground service entries are necessary
to the Incoming Switchgear Room,
132 kV Substation and Chlorine Store (I) and (II), the entry point should
be sealed to prevent
gas entry. In addition, any below grade cable trenches entering the Incoming Switchgear Room
and 132 kV Substation can become
the pathway for landfill gas and hence
grilled metal covers should
be used. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
|
S12.7 |
It is recommended regular landfill gas monitoring should
be carried out
at the Incoming Switchgear
Room, 132 kV Substation and Chlorine Store (I) and (II). The monitoring frequency will be monthly for the
first year of operation. If the
monitoring results show
no sign of landfill gas migration, reduce the monitoring frequency to once
every six months. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
N/A |
|
S12.7 |
The manholes and utility pits within the Project Site and along the
fresh water mains. Each manhole/
utility pit should be monitored with two measurements
(at mid depth and base). Each measurement should be monitored for a minimum of 10 minutes. A steady reading and
peak reading should be recorded at
each manhole/ utility pit and for each measurement. The need for venting
the manhole/ utility
pit and further monitoring will
be reviewed after
the initial monitoring. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
S12.7 |
All construction, operation and maintenance personnel working on-site as well as visitors should
be made aware
of the hazards
of landfill gas and its possible presence on-site. This should
be achieved through
a combination of posting warning
signs in prominent places and also by access
to detailed information on landfill gas hazards and the designs and procedural means
by which these hazards are being minimized on-site. |
All area/ Detailed design/ During
construction/ During operation |
Contractor(s) |
ü |
ü |
ü |
Implemented |
|
Note: D - Design stage C - Construction O - Operation
Appendix D
Water Quality Graphical
Presentation
Appendix E
Site Inspection Proforma
Date |
Environmental Observations |
Follow-up Status |
March 2020 |
||
17 March 2020 |
Observation(s) and Recommendation(s) 1. Opened cement¡¦s package was observed. It should be removed to prevent dust emission. |
1. Cement¡¦s package removed to waste temporary storage area. |
24 March 2020 |
No Major observation was observed. |
Nil |
30 March 2020 |
||
April 2020 |
||
7 April 2020 |
No Major observation was observed. |
Nil |
14 April 2020 |
||
21 April 2020 |
||
29 April 2020 |
Observation(s) and Recommendation(s) 1. The chemical (i.e. bleach) should be placed in the proper storage area. |
1. The chemical was removed and stored in proper storage area. |
May 2020 |
||
5 May 2020 |
Observation(s) and Recommendation(s) 1. Dust suppression mitigations were not implemented during construction activities. 2. Drip tray was observed without a plug / stopper. It should be added to prevent the leakage of chemicals. 3. NRMM label was not observed on the NRMM (crawler crane). 4. Chemical stain was observed on ground. |
1. Water spraying for dust suppression. 2. Plug provided. 3. NRMM label provided. 4. Chemical stain removed and temporary stored at chemical waste storage. |
13 May 2020 |
Observation(s) and Recommendation(s) 1. Dust suppression mitigations were not implemented. Follow up actions should be implemented on dusty stock piles to reduce dust emissions. |
1. Cover provided for stockpile |
19 May 2020 |
No Major observation was observed. |
Nil |
27 May 2020 |
Date |
Environmental Observations |
Follow-up Status |
June 2020 |
||
2 June 2020 |
Observation(s) and Recommendation(s) 1. Stagnant water was observed inside the drip tray. The stagnant water should be cleaned after raining. |
1. The stagnant water had cleaned. |
8 June 2020 |
No Major observation was observed. |
Nil |
17 June 2020 |
||
23 June 2020 |
||
30 June 2020 |
||
July 2020 |
||
2 July 2020 |
No Major observation was observed. |
Nil |
14 July 2020 |
Observation(s) and Recommendation(s) 1. Chemicals drums were not placed inside a drip tray t 132kV and combined shaft area. |
1. Chemical drums were removed or placed inside drip tray. |
21 July 2020 |
No Major observation was observed. |
Nil |
29 July 2020 |
||
August 2020 |
||
4 August 2020 |
No Major observation was observed. |
Nil |
11 August 2020 |
||
18 August 2020 |
||
27 August 2020 |
||
September 2020 |
||
1 September 2020 |
No Major observation was observed. |
Nil |
8 September 2020 |
||
16 September 2020 |
||
25 September 2020 |
||
29 September 2020 |
Observation(s) and Recommendation(s) 1. Chemical were not placed inside the dip- tray at the RO area. |
1. Chemical removed off site for proper storage. |
Date |
Environmental Observations |
Follow-up Status |
October 2020 |
||
6 October 2020 |
No Major observation was observed. |
Nil |
14 October 2020 |
||
20 October 2020 |
Observation(s) and Recommendation(s) 1. Stock of more than 20 bags of cement/dry pulverized fuel ash was not covered /enclosed in an area with 3 sides covered at Combine Shaft Area. (Observation) |
1. Cover was provided. |
30 October 2020 |
Observation(s) and Recommendation(s) 1. Housekeeping was reminded as C&D materials and general wastes were observed not stored properly in designed containers at ActifDAFF and RO areas. (Observation) |
1. Housekeeping was conducted. |
November 2020 |
||
3 November 2020 |
No Major observation was observed. |
Nil |
10 November 2020 |
Observation(s) and Recommendation(s) 1. Some connections of the silt curtain were observed detached and may reduce the subsequent filtering efficiency of dusty materials generated from the construction site. (observation) |
1. Connections of slit curtain were repaired. |
18 November 2020 |
No Major observation was observed. |
Nil |
26 November 2020 |
No Major observation was observed. |
Nil |
December 2020 |
||
1 December 2020 |
No Major observation was observed. |
Nil |
8 December 2020 |
No Major observation was observed. |
Nil |
15 December 2020 |
No Major observation was observed. |
Nil |
22 December 2020 |
No Major observation was observed. |
Nil |
30 December 2020 |
No Major observation was observed. |
Nil |
January 2021 |
||
5 January 2021 |
No Major observation was observed. |
Nil |
12 January 2021 |
No Major observation was observed. |
Nil |
Date |
Environmental Observations |
Follow-up Status |
19 January 2021 |
No Major observation was observed. |
Nil |
29 January 2021 |
No Major observation was observed. |
Nil |
February 2021 |
||
2 February 2021 |
No Major observation was observed. |
Nil |
9 February 2021 |
No Major observation was observed. |
Nil |
18 February 2021 |
No Major observation was observed. |
Nil |
24 February 2021 |
No Major observation was observed. |
Nil |
March 2021 |
||
2 March 2021 |
Observation(s) and Recommendation(s) 1. Chemicals were not placed inside a drip tray near the Product Water Storage Tank (observation). |
1. Chemical removed and stored in proper storage |
9 March 2021 |
Observation(s) and Recommendation(s) 1. Chemicals were not placed on a drip tray at Combined Shaft Area, Product Water Storage Tank and Formwork Storage Area (observation). |
1. Chemical removed and stored in proper storage |
16 March 2021 |
No Major observation was observed. |
Nil |
23 March 2021 |
No Major observation was observed. |
Nil |
30 March 2021 |
No Major observation was observed. |
Nil |
Appendix
F
Waste Flow Table
Appendix H
Summary of Exceedance
Table G1 Cumulative Statistics on Exceedances
Environmental Monitoring |
Parameter |
No. of non-Project related exceedance in the reporting period |
Total No. of non- Project related exceedance in the reporting period |
No. of Project related exceedance in the reporting period |
Total No. of Project related exceedance in the reporting period |
Total No. recorded since the project commencement |
||
AL |
LL |
AL |
LL |
|||||
Noise |
Leq (30min) |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Water Quality |
DO |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SS |
6 |
1 |
7 |
0 |
0 |
0 |
7 |
|
pH |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Landfill Gas |
O2 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
CH4 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
|
CO2 |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Appendix H
Complaint Log
Statistical Summary
of Environmental Complaints
Reporting Period |
Environmental
Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
16 March
2020 - 31 March
2021 |
0 |
0 |
N/A |
Statistical Summary
of Environmental Summons
Reporting Period |
Environmental Summons
Statistics |
||
Frequency |
Cumulative |
Details |
|
16 March
2020 - 31 March
2021 |
0 |
0 |
N/A |
Statistical Summary
of Environmental Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Details |
|
16 March
2020 - 31 March 2021 |
0 |
0 |
N/A |
Appendix I
Event/ Action Plan for Noise and Water Quality Monitoring Exceedance
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action
Level |
1.
Carry out investigation to
identify the source and cause of
the complaint/ exceedance(s) 2. Notify
IEC, ER, and Contractor and report the results of investigation to the Contractor, ER and the IEC 3.
Discuss with the Contractor and IEC for remedial
measures required 4. If the complaint is related to the Project, conduct additional monitoring for checking mitigation effectiveness and report the findings and results to the IEC, ER and the Contractor |
1. Review
the analyzed results submitted by
the ET 2. Review
the proposed remedial measures by the
Contractor and advise the ER
accordingly 3.
Supervise the implementation of remedial measures |
1. Confirm
receipt of Notification of Exceedance
in writing 2.
Require Contractor to propose remedial measures for the
analyzed noise problem 3. Ensure
remedial measures are properly implemented |
1. Submit
noise mitigation proposals, if required, to the
IEC and ER 2.
Implement noise mitigation
proposals |
Limit
Level |
1. Carry
out investigation to identify the source
and cause of the exceedance 2.
Notify IEC, ER, Project Proponent,
EPD and Contractor 3.
Repeat measurements to confirm findings 4.
Provide investigation report to IEC, ER, EPD
and Contractor he causes of the exceedances 5.
If the exceedance is related to
the Project, assess effectiveness
by additional monitoring 6. Report
the remedial action implemented and
the additional monitoring results
to IEC, EPD, ER and Contractor 7.
If exceedance stops, cease additional monitoring |
1.
Review the analyzed results submitted by the ET 2.
Discuss the potential remedial measures with ER, ET Leader and Contractor 3.
Review Contractors remedial actions whenever necessary to
assure their effectiveness and advise
the ER accordingly 4. Supervise
the implementation of remedial measures |
1. Confirm
receipt of Notification of Exceedance
in writing 2. Require
the Contractor to propose remedial measures for the analyzed noise problem 3.
Ensure remedial measures are properly implemented 4.
If exceedance continues, consider what activity of the work is responsible and instruct the Contractor, in agreement with the Project Proponent, to stop that activity of work until the exceedance is abated |
1. Take immediate action to avoid
further exceedance 2. Submit
proposals for remedial actions to
IEC and ER within 3 working days of notification 3.
Implement the agreed proposals 4.
Resubmit proposals if problem still not under control 5.
Stop the relevant activity of works as determined by the Project Proponent until the exceedance is abated |
Event |
Action |
|||
ET |
IEC |
Contract(s) |
ER |
|
Action Level being exceeded by one
sampling day |
1.
Repeat in situ measurement on the next
day of exceedance to confirm findings; 2.
Check monitoring data, plant, equipment and Contractor(s)¡¦s working
methods; 3.
Identify source(s) of impact and record in notification of exceedance; 4.
Inform
IEC, Contractor(s) and ER. |
1.
Check monitoring data submitted by ET and Contractor(s)¡¦s working methods; 2.
Inform
EPD. |
1. Confirm receipt of notification
of exceedance in writing; 2. Check plant and equipment and rectify unacceptable practice |
1. Confirm receipt of notification of exceedance in writing. |
Action Level being exceeded by two or more consecutive
sampling days |
1.
Repeat in
situ measurement on the next day
of exceedance to confirm findings; 2.
Check monitoring data, plant, equipment and Contractor(s)¡¦s working
methods; 3.
Identify source(s) of impact and record in notification of exceedance; 4.
Inform
IEC, Contractor(s) and ER; 5.
Discuss with IEC and Contractor(s) on
additional mitigation measures and ensure that they are implemented |
1.
Check monitoring data submitted by ET and Contractor(s)¡¦s working methods; 2.
Inform
EPD; 3.
Discuss with ET and Contractor(s) on
additional mitigation measures and advise ER accordingly; 4.
Assess the effectiveness of the
implemented mitigation measures |
1.
Confirm receipt of notification of exceedance in writing; 2.
Check
plant and equipment and rectify unacceptable practice; 3.
Consider changes of working methods; 4.
Discuss with ET and IEC on additional mitigation measures and propose them
to ER within 3 working days; 5.
Implement the agreed |
1.
Confirm receipt of notification of exceedance in writing; 2.
Discuss with the IEC on the proposed
additional mitigation measures and agree on the mitigation measures to be implemented. 3.
Ensure additional mitigation measures
are properly implemented. |
Limit Level being exceeded by one sampling day |
4.
Repeat in
situ measurement on the next day
of exceedance to confirm findings; 5.
Check monitoring data, plant, equipment and Contractor(s)¡¦s working
methods; 6.
Identify source(s) of impact and record in notification of exceedance; 7.
Inform
IEC, Contractor(s) and ER; 8.
Discuss with IEC and Contractor(s) on additional mitigation measures |
1.
Check monitoring data submitted by ET and Contractor(s)¡¦s working methods; 2.
Inform
EPD; 3.
Discuss with ET and Contractor(s) on
additional mitigation measures and advise ER accordingly; 4.
Assess the effectiveness of the
implemented mitigation measures. |
1.
Confirm receipt of notification of exceedance in writing; 2.
Check
plant and equipment and rectify unacceptable practice; 3.
Critically review the need to change
working methods; 4.
Discuss with ET and IEC on additional mitigation measures and propose them
to ER within 3 working days; 5.
Implement the agreed |
1.
Confirm receipt of notification of exceedance in writing; 2.
Discuss with the IEC on the proposed
additional mitigation measures and agree on the mitigation measures to be implemented. 3.
Ensure additional mitigation measures
are properly implemented. |
Event |
Action |
|||
ET |
IEC |
Contract(s) |
ER |
|
|
and ensure that they are implemented |
|
|
4. Request Contractor(s) to critically review the working methods. |
Limit
Level being exceeded by two or more consecutive sampling days |
1.
Repeat
in situ measurement on the
next day of exceedance to confirm findings; 2.
Check monitoring data, plant, equipment and Contractor(s)¡¦s working
methods; 3.
Identify source(s) of impact and record in notification of exceedance; 4.
Inform
IEC, Contractor(s) and ER; 5.
Discuss with IEC and Contractor(s) on
additional mitigation measures and ensure that they are implemented |
1.
Check monitoring data submitted by ET and Contractor(s)¡¦s working methods; 2.
Inform
EPD; 3.
Discuss with ET and Contractor(s) on
additional mitigation measures and advise ER accordingly; 4.
Assess the effectiveness of the
implemented mitigation measures. |
1.
Confirm receipt of notification of exceedance in writing; 2.
Check
plant and equipment and rectify unacceptable practice; 3.
Critically review the need to change
working methods; 4.
Discuss with ET and IEC on additional mitigation measures and propose them
to ER within 3 working days; 5.
Implement the agreed mitigation measures. 6.
As directed by ER, slow down or stop all or part of the marine construction works/ production volume
of the desalination plant until no exceedance of Limit Level. |
1.
Confirm receipt of notification of exceedance in writing; 2.
Discuss with the IEC on the proposed
additional mitigation measures and agree on the mitigation measures to be implemented. 3.
Ensure additional mitigation measures
are properly implemented. 4.
Request Contractor(s) to critically
review the working methods; 5.
Consider and instruct, if necessary,
the Contractor(s) to slow down or to stop
all or part
of the marine construction works/production volume of the desalination plant until no exceedance of Limit
Level. |